Monday, 10/8 – Mill Sweetbriar Court and Staats Farm Road  – COMPLETED

Tuesday, 10/9 – Pave Sweetbriar Court and Staats Farm Road – COMPLETED

Wednesday, 10/10 – Mill Pike Run Road from the bridge to Taggert Drive – COMPLETED

Friday, 10/12 – Pave Pike Run Road from the bridge to Taggert Drive (Complete line striping on Mon., 10/15)

Monday, 10/15 – Mill and Pave Bridgepoint from Rt. 206 to four-way stop with Millstone River Road

Monday, 10/15 – Pave Broadway

Tuesday, 10/16 – Mill Bedens Brook from the bridge to Country Club Drive (Single lane of traffic access will be maintained.)

Wednesday, 10/17 – Pave Bedens Brook from the bridge to Country Club Drive (Single lane of traffic access will be maintained.)

Please follow all Police detours and directions. It is anticipated that most projects will be only for a day or two, but completion time is weather-dependent. We appreciate your patience.

To receive timely road work and emergency updates from Montgomery Township Police as texts or emails, sign-up for Nixle at: http://local.nixle.com/montgomery-police/

Thank you,

Montgomery Township Police Department
Montgomery Township Dept. of Public Works